|





 




|
|
|
WHAT
WE DO

Phase
I - Pre-Planning and
Pre-Design
(1 week)
|
Client provides a program describing the scope of the
project and its included elements, including a statement of
objectives, marketing and site data, and all jurisdictional
requirements. This program will be the basis of the
project's design for all further phases. |
|
 |
|
|
|
|
LGS Architects reviews the submitted program to become
familiar with the project and come to a mutual agreement
with the Client on requirements and objectives. LGS
Architects then ensures that project complies with current
ordinances and regulations. |
|
 |
|
|
|

Phase
II - Schematic Design Phase
(Conceptual, 2 weeks; Actual, 1 week)
|
LGS Architects prepares several sets of conceptual design
studies for Client's review, comment, and
approval. |
|
 |
|
|
|
|
Once Client selects one set of conceptual design studies,
LGS Architects prepares one set of floorplans illustrating
layout and size aspects for Client's review, comment, and
approval. |
|
|

Phase
III - Site Planning
(1 week)
|
Client provides a finished tract map of project.
• Building footprints, to be plotted by a civil engineer on the tract map, are prepared by LGS Architects.
|
|
 |
|
|
 |
|
|
 |

Phase
IV - Preliminary Design
Phase
(2 weeks)

Phase
V - Design Development
Phase
(2 weeks)
|
LGS Architects prepares detailed design development drawings
for all plans and establishes preliminary material and
construction standards, both for Client review, comments,
and approval. |
|
 |
|
|
|
| • LGS Architects attends a Value Engineering conference to review project designs with the Client and key subcontractors. |
|
 |

Phase
VI - Presentation Phase
(2 weeks)
| • Color boards, Color Application Booklet
LGS Architects prepares illustrated exhibits, including
floorplans, exterior elevations, and color schemes, to
present to the required jurisdictional government offices
for approval. Client also may use these exhibits for
promotional purposes.
|
|
 |
|
|
|
|
|
 |

Phase VII - Construction Document Phase (4
weeks)
|
LGS Architects prepares construction documents following
local building codes and other jurisdictional requirements.
These documents allow for the Client to obtain a building
permit. |
|
 |
|
|
 |
|
|
 |
|
|
 |

Phase
VIII - Plan Check Phase
(Varied)
|
Construction documents are submitted to the Building
Department for a plan check. Required corrections are made
by LGS Architects. An office plan check is also conducted by
LGS Architects, to help minimize errors. |
|
 |
|
The Client notifies LGS Architects of any perceived
errors/omissions in plans. LGS Architects will provide
written instructions addressing these concerns; it is the
Client's responsibility to follow these instructions.
LGS Architects reviews work of structural engineers, M.E.C.
consultant, etc. working on project for compliance with
architectural standards of project.
|
|
 |
|
|
|
|
|
|
|
|

Phase
IX - Construction Phase
(Varied)

Extras
• LGS Architects offers additional services throughout this process at an extra fee.
Please contact LGS Architects to learn more about these
services.
|
|
|

|



 |
|
| • This timeline is not a complete schedule of information and should not be considered a substitute for the actual Client-Architect contract agreement. Please contact LGS Architects for further details. |
|
|
|
|
|
|
|